Work halted on part of $9B Honolulu rail project due to incomplete design constructiondive.com - get the latest breaking news, showbiz & celebrity photos, sport news & rumours, viral videos and top stories from constructiondive.com Daily Mail and Mail on Sunday newspapers.
Updated 12/16/20, 1:21 p.m.
The state Department of Health reported 110 new cases and four fatalities today.
According to the state s numbers, Oʻahu had 85 new cases, Maui 14, Hawaiʻi County 5, Kauaʻi, Lanai and Molokaʻi had none.
The latest state counts bring the Oʻahu total to 16,543, Hawaiʻi County 1,748, Maui 728, Kauaʻi 134, Lanai 106 and Molokaʻi 22. The number of out-of-state cases totals 309.
Since the pandemic began, the state has tallied 19,590 cases. The death toll stands at 278.
Department of Education furloughs start on Jan. 4
January 4 will be the first day of furloughs for employees of the state Department of Educatoin.
Honolulu Rapid Transit Facebook Page / HART
Details of the two bids to construct and manage the final 4.2 miles of Honolulu s rail project have been released. The priority listed offerors (PLO) bidding on the city center project were City Center Connection Group and Imua Transit Honolulu.
According to the city, both bids were more than a billion dollars higher than the affordability limit the highest the city was willing to accept to design and build the rail project from Dillingham Boulevard to Ala Moana Center. Both came in . . . almost $1.3 billion above the affordability limits. That was 60% higher than anticipated, said Mayor Kirk Caldwell during a press conference yesterday afternoon. And to get that price down, it would be nearly impossible.
Honolulu Rapid Transit Facebook Page / HART
Details of the two bids to construct and manage the final 4.2 miles of Honolulu s rail project have been released. The priority listed offerors (PLO) bidding on the city center project were City Center Connection Group and Imua Transit Honolulu.
According to the city, both bids were more than a billion dollars higher than the affordability limit the highest the city was willing to accept to design and build the rail project from Dillingham Boulevard to Ala Moana Center. Both came in . . . almost $1.3 billion above the affordability limits. That was 60% higher than anticipated, said Mayor Kirk Caldwell during a press conference yesterday afternoon. And to get that price down, it would be nearly impossible.