Proposed Natural Gas Plant For Superior Doesn t Need MN Review
kool1017.com - get the latest breaking news, showbiz & celebrity photos, sport news & rumours, viral videos and top stories from kool1017.com Daily Mail and Mail on Sunday newspapers.
MEPA Review Not Required as Part of Wisconsin Gas Plant Affiliated-Interest Agreements, Says Minnesota Supreme Court | Stoel Rives - Renewable + Law
jdsupra.com - get the latest breaking news, showbiz & celebrity photos, sport news & rumours, viral videos and top stories from jdsupra.com Daily Mail and Mail on Sunday newspapers.
Power Plants
courthousenews.com - get the latest breaking news, showbiz & celebrity photos, sport news & rumours, viral videos and top stories from courthousenews.com Daily Mail and Mail on Sunday newspapers.
ADVERTISEMENT
ADVERTISEMENT
Minn. High Court Says Enviro Study Of Gas Plant Not Needed
Law360 (April 22, 2021, 5:59 PM EDT) Minnesota s highest court ruled in a 6-1 decision that state regulators weren t required to conduct an environmental review of utility Minnesota Power s agreements with an out-of-state affiliate for the construction and operation of a power plant on Wisconsin soil.
In the divided decision Wednesday, the majority reversed a lower appellate court s ruling that the Minnesota Public Utilities Commission should have conducted an environmental review before approving Minnesota Power s request to help fund the construction of a $700 million gas-fired power plant, called the Nemadji Trail Energy Center, or NTEC, across the border in Wisconsin.
The decision reverses a lower court s ruling. 1:19 pm, Apr. 21, 2021 ×
Minnesota Power and Dairyland Power Cooperative have proposed a $700 million natural-gas power plant, Nemadji Trail Energy Center, which would be located near the Husky refinery in Superior and provide 525-625 megawatts of power. (Photo courtesy of Minnesota Power)
Minnesota regulators do not need to prepare an environmental review for Minnesota Power s proposed $700 million natural gas power plant planned for Superior, the Minnesota Supreme Court decided Wednesday, reversing a lower court s 2019 decision.
Writing for the majority, Justice Anne K. McKeig said the Minnesota Court of Appeals erred in its December 2019 decision that said the Minnesota Public Utilities Commission should have considered the potential impacts Minnesota Powers proposed Nemadji Trail Energy Center, or NTEC, could have on air, water, land and other natural resources even though it is proposed for Wisconsin.