Soon to take your breath away: Bicol International Airport nearing completion : vimarsana.com

Soon to take your breath away: Bicol International Airport nearing completion


(DOTr FACEBOOK / MANILA BULLETIN)
Currently, the overall progress of construction at the BIA has been pegged at 74.132 percent complete. Actual construction work at the airport only started in December 2016.
But now, Department of Transportation (DOTr) Secretary Arthur P. Tugade has ordered the conduct of continuous or 24/7 construction, and to do what is necessary to ensure faster completion of the project.
As of Feb. 3 2021, Package 2A of the BIA development project is 89.784 percent complete.
Construction works in Package 2A cover the airport’s landside facilities, such as the Administration Building, Air Traffic Control Building, Crash Fire Rescue Building, and the Maintenance Building.

Related Keywords

Mayon Volcano , Philippines General , Philippines , Bicol , Camarines Sur , Arthurp Tugade , , Bicol International Airport , Department Of Transportation Dotr , Administration Building , Secretary Arthur , Air Traffic Control Building , Crash Fire Rescue Building , மேயன் எரிமலை , பிலிப்பைன்ஸ் ஜநரல் , பிலிப்பைன்ஸ் , செயலாளர் ஆர்தர் , அேக போக்குவரத்து கட்டுப்பாடு கட்டிடம் , செயலிழப்பு தீ மீட்பு கட்டிடம் ,