Carnac Bridge Demolition: 75 days of planning for 27-hour exercise of dismantling Mumbai's iconic structure
The last fortnight has been of intense activity to ensure things are going according to plan.
Source: freepressjournal.in
Stay updated with breaking news from Carnac Bridge. Get real-time updates on events, politics, business, and more. Visit us for reliable news and exclusive interviews.
The last fortnight has been of intense activity to ensure things are going according to plan.
The Carnac Bridge block will double up for track renewal, signalling maintenance, overhead electrical wire maintenance and cleanliness works.
The 27 hours mega block will start at 11.00 pm on Nov 19 and will end at 2.00 am on Nov 21
For the convenience of passengers, CR has already requested concerned municipalities to arrange additional buses in block affected areas.