Downpour: Lagos-Ibadan Expressway April 30 delivery still holds
April 30 delivery of the Lagos-Ibadan Expressway reconstruction/rehabilitation Project is set although construction on three of the 43.6km of Section One could not be completed due to heavy rainfall and other factors. The Federal Controller of Works in Lagos State, Mr Umar Bakare, made the disclosure on Saturday night in a telephone interview with the