Stay informed with the latest breaking news from Kalnai hydroelectric project on our comprehensive webpage. Get up-to-the-minute updates on local events, politics, business, entertainment, and more. Our dedicated team of journalists delivers timely and reliable news, ensuring you're always in the know. Discover firsthand accounts, expert analysis, and exclusive interviews, all in one convenient destination. Don't miss a beat — visit our webpage for real-time breaking news in Kalnai hydroelectric project and stay connected to the pulse of your community

SAC's decision remains unimplemented even after lapse of over 2 and half years - Jammu Kashmir Latest News | Tourism

Re-tendering of Lower Kalnai Hydroelectric Project in Doda PDC fails to tap potential during past nearly 13 yrs Mohinder Verma JAMMU, Feb 20: In a testimony of dilly-dallying and non-serious approach towards tapping power potential, the Jammu and Kashmir Power Development Corporation has failed to implement the decision of the State Administrative Council (SAC) regarding re-tendering of 48 Mega Watt (MW) Lower Kalnai Hydroelectric Project in Doda district despite lapse of over two and half years. The State Administrative Council […]

Jammu , Jammu-and-kashmir , India , Kalnai , Chhattisgarh , Kashmir , Mohinder-verma , Raja-yaqoob-farooq , Mega-watt , Satya-pal-malik , Power-development-department , Administrative-council

Four power projects of nearly 2000 MW in J&K facing time overrun of 5 to 8 yrs


Four power projects of nearly 2000 MW in J&K facing time overrun of 5 to 8 yrs
Four power projects of nearly 2000 MW in J&K facing time overrun...
Four power projects of nearly 2000 MW in J&K facing time overrun of 5 to 8 yrs
Several major reasons identified for delay in completion
Mohinder Verma
JAMMU, July 29: Four power projects of nearly 2000 Mega Watts (MW) capacity in the Union Territory of Jammu and Kashmir are facing time overrun of five to eight years because of host of reasons and in order to ensure that they are completed within the anticipated time-frame Union Power Ministry is initiating steps for resolution of all the outstanding issues.

Jammu , Jammu-and-kashmir , India , Mohinder-verma , Mega-watts , Union-power-ministry , Union-territory-of-jammu , Central-electricity-authority , Power-ministry , Union-ministry-of-power , Union-territory , Pakal-dul-hydroelectric-project