South Fork OWF Draft EIS Out | Offshore Wind
January 6, 2021, by Adrijana Buljan The U.S. Bureau of Ocean Energy Management (BOEM) has published a Draft Environmental Impact Statement (EIS) for the South Fork offshore wind farm and will open a 45-day public comment period on 8 January. After the public consultation period, BOEM will address all received comments and publish a Final EIS, which is expected to be done in August, with the environmental review and permitting process anticipated to be completed in January 2022. The South Fork Draft EIS incorporates the expanded cumulative scenario and anal...