Rameswaram-Dhanushkodi rail link remains a non-starter
Project cost has gone up as experts have recommended elevated embankment Two years after Prime Minister Narendra Modi laid the foundation stone for the Rameswaram-Dhanushkodi railway line, work is yet to commence on the 17.2-km stretch, as officials await the sanctioning of the revised cost estimate, which has more than tripled. Only the survey work for the project has been completed. After engineers from IIT-Madras recommended an elevated embankment of about six-seven metres above road level, the original estimate of ₹208 crore was revised upwards to ₹700 crore, sources in the Southern R...