Kamoa-Kakula Copper Mine achieved Phase 1 commercial production on July 1, 2021; first phase projected to produce approximately 200,000 tonnes of copper per yearKamoa-Kakula's Phase 2 expansion, scheduled
Kamoa-Kakula Copper Mine achieved Phase 1 commercial production on July 1, 2021; first phase projected to produce approximately 200,000 tonnes of copper per year Kamoa-Kakula's Phase 2 expansion, scheduled for Q3 2022, will double annual copper output to approximately 400,000 tonnes Ivanhoe Mines pledges net-zero greenhouse gas emissions at the Kamoa-Kakula Copper Mine Good progress being made on Ivanhoe's Western .
Project Coordinator-DRSLPII reliefweb.int - get the latest breaking news, showbiz & celebrity photos, sport news & rumours, viral videos and top stories from reliefweb.int Daily Mail and Mail on Sunday newspapers.
Copper production at the Kamoa-Kakula Mine to begin imminently; first phase projected to produce approximately 200,000 tonnes of copper per year Kamoa-Kakula's Phase 2 expansion, scheduled for Q3 2022, will double annual copper output to approximately 400,000 tonnes Ivanhoe Mines pledges net-zero greenhouse gas emissions at the Kamoa-Kakula Copper Mine Expanded 2021 exploration program underway on Ivanhoe's Western .
Ivanhoe Mines Ltd.: Ivanhoe Mines Issues Q1 Financial Results and Review of Mine Construction Progress and Exploration Activities
80,000 to 95,000 tonnes
All figures in the above table are on a 100%-project basis. Metal reported in concentrate is prior to refining losses or deductions associated with smelter terms. Cost guidance is expected to be provided once the Kamoa-Kakula Project s Phase 1 plant has reached steady state production.
Kamoa-Kakula s Phase 1 backfill plant with concentrator plant in the background.
To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/83893 8fb1019064489b13 006full.jpg
Construction of Phase 2 of the Kamoa-Kakula project is well underway and Phase 3 expansion is being explored