Liberia: Investigative Report over Burning of Turbine at Mount Coffee Hydro in Limbo; Stakeholders ‘Dodging’ Responsibility
Liberia: Investigative Report over Burning of Turbine at Mount Coffee Hydro in Limbo; Stakeholders ‘Dodging’ Responsibility
Share
MONROVIA – Two of the four turbines at the Mount Coffee Hydro have been down and the Government of Liberia is yet to know what led to the damage, despite series of investigations commissioned by the manufacturer and the insurance company.
FrontPageAfrica gathered from sources familiar with the development within the Liberia Electricity Corporation (LEC) that while one of the turbines was shut down due to oil leakage, the other got burnt in February, thereby, reducing the capacity of the hydro from 88 megawatts to 44 megawatts.