New drone footage released today of the Matakana Link Road construction shows the significant progress being made on this major project.
Over 333 truck and trailer loads of drainage metal have now been supplied â which would fill a rugby field to a depth of approximately 1m.
Erosion controls are now 100 per cent complete; while site clearing and tree felling is 98 per cent complete.
Matakana Road overhead services have now all been placed underground.
[embedded content]
Auckland Mayor Phil Goff welcomes the progress on the project, which he says is coming in on time and on budget.
âThe Matakana Link Road will ease congestion around Hill Street and make things easier for people travelling to and from Leigh, Omaha, Sandspit and Snellâs Beach,â he says.