The National Grid Corporation of the Philippines (NGCP) has completed its P7.09-billion Mindanao backbone after it energized the project’s final component.
In a statement on Thursday, the NGCP said it recently energized the Toril-Bunawan 230 kilovolt (kV) transmission line, the final component of its Mindanao 230-kilovolt (kV) backbone project.
The project, the grid operator said, will secure the reliability of power transmission services in the entire Mindanao.
“As one of NGCP's critical projects, the Mindanao backbone will connect bulk generation from the northern and southern parts of Mindanao and ensure stable and continuous power from Lanao del Norte, passing through Misamis Oriental and Bukidnon, all the way to Davao del Sur and Davao Occidental,” it said.

Related Keywords

Maramag ,Eastern Samar ,Philippines ,Balo I ,Philippines General ,Misamis Oriental ,Davao Del Sur ,Malita ,Matanao ,Davao ,Davao City ,Lanao Del Norte ,Toril ,Bukidnon ,Sagay City ,Visayas ,The Philippines , ,National Grid Corporation Of The Philippines ,San Miguel Consolidated Power Corporation ,Therma South Incorporated Power Plant ,National Grid Corporation ,Davao Occidental ,Kauswagan Clean Coal Fired Power Plant ,Villanueva Substation ,Baloi Villanueva Lines ,Bunawan Substation ,Maramag Villanueva Line ,Toril Substation ,Mindanao Visayas Interconnection Project ,Mindanao Backbone ,கிழக்கு சமர் ,பிலிப்பைன்ஸ் ,பலோ நான் ,பிலிப்பைன்ஸ் ஜநரல் ,தவோ டெல் சூர் ,தவோ ,தவோ நகரம் ,லானோ டெல் நார்ட் ,டரில் ,விசயாஸ் ,தி பிலிப்பைன்ஸ் ,தேசிய கட்டம் நிறுவனம் ஆஃப் தி பிலிப்பைன்ஸ் ,சான் மிகுவல் தொகுக்கப்பட்டு பவர் நிறுவனம் ,தெர்மா தெற்கு இணைக்கப்பட்டது பவர் ஆலை ,தேசிய கட்டம் நிறுவனம் ,தவோ தற்செயலானது ,விலந்வெவ துணை மின்நிலையம் ,பலோய் விலந்வெவ கோடுகள் ,டரில் துணை மின்நிலையம் ,

© 2025 Vimarsana

vimarsana.com © 2020. All Rights Reserved.