The massive re-building of Upper Broadway continues to progress through Phase 1, with crews now at Cary Avenue and one-third of the way done on their trek to the Revere City Line. The DPW’s Fidel Maltez said the water and sewer replacement work that started in September is divided up into three zones, and crews are now 100 percent done with the zone from City Hall to Cary Avenue. A 12-inch PVC Sewer Main installation. approximately 10 feet deep. “Now we’re doing Cary Avenue to Webster,�...