Matiang i Acts as KeNHA Complains Chinese Delay in Ksh4 4B Project

Matiang i Acts as KeNHA Complains Chinese Delay in Ksh4.4B Project 3 March 2021 - 11:44 am Interior CS Fred Matiang i speaks at the National Chief s Forum in Nairobi on Friday, July 3, 2020 File Interior Cabinet Secretary Fred Matiang i has intervened after the Kenya National Highways Authority (KeNHA)  decried slow progress of a Ksh4.4 Billion road project. The roads agency had earlier expressed concern that the contractor, China State Corporation Contractors Limited, would not complete Kitale-Suam road that transverses Trans Nzoia County within the set timelines. The 45-kilometre road was initially to be completed by August 2020 but the revised completion period is February 25, 2022. Tarmacking of 45km Kitale-Endebes-Suam road in August 2020.