The association has said flat owners are not ready to pay the fee of Rs 1,000 per sq ft for rebuilding the towers as offered by the developer. For reconstruction of flats, the flat owners who have not accepted buyback option will have to pay Rs 1,000 per sq ft in four instalments — 40% at the start of construction, 30% on completion of basic structure, 20% while applying for occupation certificates (OCs) and remaining 10% before possession.
65 Gurugram highrises have structural faults: RWAs newindianexpress.com - get the latest breaking news, showbiz & celebrity photos, sport news & rumours, viral videos and top stories from newindianexpress.com Daily Mail and Mail on Sunday newspapers.
In February 2022, a large portion of an apartment on the 6th floor of tower D collapsed to the first floor, killing two. Since then, the Deputy Commissioner asked residents of towers D, E, F, G, and H to vacate as the structural audit reports of the towers showed they were unfit for habitation.
Six floors of Tower D of Chintels Paradiso society had collapsed partially on February 10, 2022 leading to the death of two female residents. Since then, the building site has been a matter of dispute between the builder and residents.
The structural audit of 22 highrise societies in Gurgaon has been stuck for the past six months as the developers have failed to pay the fee. Notices are being issued to the developers warning them of legal action. Only one society has paid the fee so far and six societies have not even shared the project drawings. Find out more about the status of the audit and the actions being taken by the district administration and DTCP.