All the work shown on december 9th, 2016. If you look at the one on the right, that was taken last week. Major differences such as the awning, and all the work thats up on the park. A lot of work has happened in 2017. What you cant tell is even the replacement of the temporary beale street bridge, as well. Going into some of the highlights of construction, all the topping slabs were completed, all by the third quarter. Doors, framing, hardware installings, all installed and for the most part. The bus stop, commuter island, all those coding systems completed. And especially the grand haul, raidi radiant heating was completed in 2017. Also, the exterior awning, the entire awning as perthis picture here is all installed. All the items, the vertical glass curtain wall, like around the grand haul or level two, all the sections west of first street are all installed. When you go up onto the roof, the w8, which is the glass canopy is also installed. And also the sky light and the glass floor
The second street, exterior sun will also be in, grading, everything so that buses can be parked. And then, the Administration Building will be completed as well. Youll hear over the next few months, ill be presenting the construction updates over the next few months. So with that, ill turn it over to skip for phase two, the 2018. So for 2018, the plan for phase two is tjpa has been requested by sfcta to put the fcis on hold until the peer review on the street track has been completed in march. We will then submit the environmental document to the board fof your approval. The seiscs is with the fta right now, and they are doing their final qcqa checks and will be in position to issue the rod prior to the tjpa board approval. We have scheduled meetings with sfta to support their review for the tier three track. And were in place, once the rap study is available, well be in a position to address any of the recommendations that are presented from this study. Were going to secure funding t
Raidi radiant heating was completed in 2017. Also, the exterior awning, the entire awning as perthis picture here is all installed. All the items, the vertical glass curtain wall, like around the grand haul or level two, all the sections west of first street are all installed. When you go up onto the roof, the w8, which is the glass canopy is also installed. And also the sky light and the glass floor up on the roof was all installed in 2017. The roof top landscaping commenced in earnest and worked hard in 2017. The trees. There are 76, over 75 of the trees installed. And Boston Properties started installing the major parts of their gondola. And the pathways, theyre almost done with that half mile pathway that goes around the entire park. Its almost completed and is going well. Onto other elements. Ac transit commenced their bus testing on the bus deck in december, and that will continue. And then, the bus plaza, we opened the 5 Fulton Service on december 26, and this picture was early