Brentwood company to construct interchange as part of massive mixed-use development effort in Spring Hill
Brentwood-based Bell and Associates Construction has won a roughly $54 million contract with the state a deal that will provide Spring Hill and Thompson’s Station more direct access to Interstate 65 and allow future development June Lake to fully unfold.
The project includes the design and construction of a new interchange on I-65 and the extension of Buckner Road, between Buckner Lane and Lewisburg Pike in the eastern part of the city. The project is expected to be complete by May 2023.
In December 2018, the U.S. Department of Transportation awarded Spring Hill a $25 million grant to help pay for the project. In order to use those funds, the project will need to be fast-tracked. By early 2019, Spring Hill had already contracted with Volkert Inc. to begin environmental clearance and preliminary engineering for the project. TDOT is also using an expedited contracting pro