£2m linkspan repair project at Gourock Ferry Terminal is to be completed by mid-February
GOUROCK LINKSPAN THE delayed £2m linkspan repair project at Gourock Ferry Terminal is to be completed by mid-February say port bosses. A revised project timetable has been announced by Caledonian Maritime Assets Limited (CMAL), which owns Gourock Ferry Terminal and is leading the reavmp. The new linkspan was scheduled to be installed in November and the project was due to be completed by the end of 2020. However, after the old linkspan was removed, additional surveys revealed issues w...