NGT stays green nod for NTPC’s Karimnagar plant
Updated:
Updated:
Environmental Clearance put on hold for seven months, bench calls for fresh appraisal.
Share Article
AAA
The NTPC Super Thermal Power project at Ramagundam in Karimnagar District of Andhra Pradesh
| Photo Credit: P V SIVAKUMAR
Environmental Clearance put on hold for seven months, bench calls for fresh appraisal.
The southern bench of the National Green Tribunal has put in abeyance the Environment Clearance (EC) granted to the 2x800 MW thermal power plant of the National Thermal Power Corporation (NTPC) in Karimnagar district in Telangana for a period of seven months or till a re-appraisal is done and additional conditions are imposed by the Ministry of Environment Forest and Climate Change (MoEF & CC) .