MBTA: accelerated Green Line D branch track and signal replacement work to take place for 18 days
MBTA: accelerated Green Line D branch track and signal replacement work to take place for 18 days May 25, 2021 MBTA undertaking over three weeks of track and signal work. MBTA The MBTA’s Green Line Transformation program (GLT) will accelerate the Green Line D Track and Signal Replacement Project to complete the most disruptive track replacement work by early fall 2021. After this milestone, signal replacement and testing will continue through the end of fall 2021 when the project is anticipat...