week in, we have a complete street closure this weekend, which will allow them to cross the southern half of the southern crossing. next week, the machine will agree mobilize down to the west end, and the two of them will work together to finish that shoring also the excavation can begin in the western section. as far as his own four, were the buttress operation is taking place, the equipment mobilized over the last month, i have some pictures of that in a moment. that drilling operati...