Breakdown of the cost increase. Note that the hard cost here is based on a rough order magnitude estimate provided by our cmt. I think whats very important to realize too is that these numbers of course are very big. But to only well to 15 of these additional costs are actual premium cost that could have been avoided would we have found fees fishures during the design phase. So if we knew about it, 85 of those costs would have actually been in our project budget originally. Why didnt we know abo...