The Sh1b 24-km road that 'can't be built because of sewage, poor drainage'
KURA representative, Eng. Benjamin Asin, who is the agency’s assistant director, said heavy rainfall pounding the area have made it impossible to continue with construction works as most parts of the road are flooded. “Construction works can only resume after rainfall subsides. The type of soil in Thika cannot allow for road-building to continue under wet circumstances,” he stated. Asin said the Authority, previously, had to deal with land encroachment, which led to delays in construction...
Source: standardmedia.co.ke