Work on RoBs in Kottayam reviewed

Work on RoBs in Kottayam reviewed Updated: Updated: Directive to issue tender for approach road work on February 2 Share Article Directive to issue tender for approach road work on February 2 Close on the heels of the steps to expedite track doubling and renovation of the Kottayam railway station, a delegation of Southern Railway officials and Thomas Chazhikadan, MP, on Wednesday reviewed the progress of work on the railway overbridges (RoB) coming up in Kottayam. During the meeting, Railways informed that work on the RoB at Mulanthuruthy had been completed as early as 2018 while work on the bridge at Carithas was on the final stages. The authorities are now awaiting nod from the Railway Safety Commissioner to carry out the remaining work on these two RoBs.