The Malawi Rural Electrification Programme (Marep Phase 9) is expected to miss the second deadline of August 2024 with authorities now eying October 2024. The project, which had been facing delays since 2020 at procurement and contracting stages, was initially planned to be completed on 31 March, 2024. In an earlier interview, Ministry of Energy
Marep 9 delays worry MPs - The Nation Online mwnation.com - get the latest breaking news, showbiz & celebrity photos, sport news & rumours, viral videos and top stories from mwnation.com Daily Mail and Mail on Sunday newspapers.
At least six companies risk being deregistered for failing to deliver after pocketing a 30 percent part-payment to supply materials for the Malawi Rural Electrification Programme (Marep) K40 billion Phase IX project. Ministry of Energy Principal Secretary Alfonso Chikuni disclosed in an interview this week that since the companies signed the Bid Securing Declaration, the