A year into the Midland Avenue reconstruction efforts in Glenwood Springs, construction crews are winding down for the winter with more than half the project in the rearview.
A year into the Midland Avenue reconstruction efforts, construction crews are winding down for the winter with more than half the project in the rearview.
A significant portion of the South Midland Avenue project could be paved by the first week of October, Gould Construction Superintendent Dave Metrovich said.
Beginning today, traffic traveling through the roundabout under construction at 4 Mile Road and South Midland Avenue will be single-lane only for the next two weeks, a Glenwood Springs news release states.