Delay in Aberdeen schools construction blamed on Covid 'fears' of builders
Construction projects up and down the country have been hit with delays due to the pandemic. Even after a three-month initial lockdown was lifted, changes in rules around the number of workers allowed within the tight confines of a building site slowed progress. Covid legacy: builders ‘reluctant’ to come to Aberdeen after last year’s local lockdown Aberdeen City Council’s chief capital officer, John Wilson, told members about how “reluctant” contractors were to visit the north-east....