During a dialogue with government officials regarding the Pain Borneo project, a Kg Kolopis villager asked, “Is the flood man-made?”
Jabatan Pengairan dan Saliran made a long-winded praise to the high intensity of rain recorded, but declined to answer if they had five year rainfall records for study and comparison.
Another question spilled the beans that none of the four flood mitigation projects in the district have been completed despite big promises way back in 2016. Only two were implemented but not completed