Copper production at the Kamoa-Kakula Mine to begin imminently; first phase projected to produce approximately 200,000 tonnes of copper per year Kamoa-Kakula's Phase 2 expansion, scheduled for Q3 2022, will double annual copper output to approximately 400,000 tonnes Ivanhoe Mines pledges net-zero greenhouse gas emissions at the Kamoa-Kakula Copper Mine Expanded 2021 exploration program underway on Ivanhoe's Western .
Ivanhoe Mines Ltd.: Ivanhoe Mines Issues Q1 Financial Results and Review of Mine Construction Progress and Exploration Activities
80,000 to 95,000 tonnes
All figures in the above table are on a 100%-project basis. Metal reported in concentrate is prior to refining losses or deductions associated with smelter terms. Cost guidance is expected to be provided once the Kamoa-Kakula Project s Phase 1 plant has reached steady state production.
Kamoa-Kakula s Phase 1 backfill plant with concentrator plant in the background.
To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/83893 8fb1019064489b13 006full.jpg
Construction of Phase 2 of the Kamoa-Kakula project is well underway and Phase 3 expansion is being explored
Ivanhoe Mines enters public-private venture with DRC’s power company to upgrade Inga II power complex By Samuel Haughton April 27, 2021
Ivanhoe said the lack of a sufficient power supply limited the company s ability to access Kamoa-Kakula s inferred resources. Courtesy of Ivanhoe Mines.
Ivanhoe Mines reported on April 26 that the Kamoa-Kakula copper project in the Democratic Republic of the Congo would receive a boost to its renewable power supply thanks to a planned upgrade to Turbine 5 at the Inga II hydropower complex.
Ivanhoe Mines Energy DRC signed a memorandum of understanding with the DRC’s state-owned power company La Société Nationale d Electricité (SNEL) to upgrade the turbine. The planned upgrade to the turbine will raise its output by an estimated 162 megawatts, part of which will go towards powering the project, with any excess added to the national power g
(MENAFN - Newsfile Corp) Kamoa-Kakula Joint-Venture Signs Agreement with the DRC s State-Owned Power Company to Upgrade Turbine 5 at the Inga II Hydropower Complex Turbine 5 to produce 162 MW of renewable hydropower, providing the Kamoa-Kakula Copper Complex and associated smelter with sustainable electricity for future expansions Democratic Republic of Congo s President Félix Tshisekedi expresses support for the Turbine 5 upgrade at Inga II Voith Hydro of Germany to be appointed as lead contractor for the Turbine 5 project Upgrading of the Mwadingusha hydropower plant is nearing completion to generate 78 MW of hydropower for the first two phases of copper production at Kamoa-Kakula Combined 240 MW output from the Mwadingusha and Inga II hydropower plants also will benefit local communities
Ivanhoe Mines Ltd : Kamoa-Kakula Joint-Venture Signs Agreement with the DRC s State-Owned Power Company to Upgrade Turbine 5 at the Inga II Hydropower Complex finanznachrichten.de - get the latest breaking news, showbiz & celebrity photos, sport news & rumours, viral videos and top stories from finanznachrichten.de Daily Mail and Mail on Sunday newspapers.