Work zones to watch for this week in Fredericksburg, Stafford Photo: VDOT
All work is scheduled weather permitting. Real-time information on work zones and lane closures is available on 511Virginia.
I-95 Southbound
Monday – Thursday, 6 a.m. – 10 a.m., Monday – Thursday, 9 p.m. – 10 a.m.
Thursday – Friday, 9 p.m. – 6 a.m. and Friday – Saturday, 10 p.m. – 7 a.m.
Single lane closure on I-95 southbound between the two interchanges for construction activities for the 95 Express Lanes Fredericksburg Extension (Fred Ex) project.
Exit 148 (Quantico) to Exit 133 (Route 17)
Monday – Thursday, 9 p.m. – 10 a.m., Thursday – Friday, 9 p.m. – 6 a.m. and
Friday – Saturday, 10 p.m. – 7 a.m. Single lane closures on I-95 southbound at various locations between the two interchanges to allow crews to adjust work zone barrier for the Fred Ex project.
Construction is progressing on a project to replace the Route 1 bridge over Potomac Creek in Stafford County, and northbound drivers can expect a slight traffic shift in the work zone beginning Monday, Feb. 15.
Travel hotspots this week in the Fredericksburg region Photo: VDOT
Exit 130 (Route 3)
Monday – Friday, 9 p.m. – 4:30 a.m. Single northbound lane closure near the Exit 130 interchange for work zone barrier installation for the I-95 Southbound Rappahannock River Crossing project.
Exit 133 (Route 17) to Exit 136 (Centreport Parkway)
Monday – Thursday, 9 p.m. – 4:30 a.m. and Friday – Saturday, 10 p.m. – 7 a.m. Single northbound lane closure near Exit 133 and Exit 136 interchanges for work zone barrier installation for the I-95 Northbound Rappahannock River Crossing project and 95 Express Lanes Fredericksburg Extension (Fred Ex) project.
Exit 143 (Aquia/Garrisonville Road) to Exit 148 (Quantico)
Monday – Thursday, 9:30 a.m. – 3:30 p.m. Single northbound lane closure between mile markers 145 and 148. Material deliveries and pile driving for the 95 Express Lanes Fred Ex project.