Adani Power has begun exporting power to Bangladesh from its 1,600MW plant in Jharkhand s Godda. The reliability run test, including commercial operation tests of the second unit of Godda power plant, was completed on June 25 in the presence of Bangladesh Power Development Board and Power Grid Corporation of Bangladesh (PGCB) officials.
Salasar Techno Engineering added 1.13% to Rs 599.50 after the company said it secured a project worth Rs 238.65 crore from Power Grid Corporation of India (PGCIL).PGCIL, vide their letter dated 22 May 2021, has awarded power projects to Salasar Techno Engineering. The orders include construction of 201 Km transmission line network and construction of 4 new power substations in the Arunachal Pradesh.
The transmission line network will be of 132KV type and the substations will be of the extra high voltage capacity. The estimated cost of the work allocated to the company is Rs 238.65 crore. It involves supply, construction, erection, testing and commissioning of transmission towers and substations.
Salasar Techno Engineering announced that Power Grid Corporation of India has awarded to the company power projects which include construction of 201 km transmission line network and construction of 4 new power substations in the north eastern state of Arunachal Pradesh.
The transmission line network will be 132 KV type and the substation will be the extra high voltage capacity.
The estimated cost of work allocated to Salasar is Rs 238.65 crore and involves supply, construction, erection testing and commissioning of transmission towers and substations.
Powered by Capital Market - Live News
(This story has not been edited by Business Standard staff and is auto-generated from a syndicated feed.)