SFGTV February 14, 2014
Agreements that are being worked out with some of the cemetery and those are taking longer than anticipated. We have a forecast of 22 months beyond the approved schedule and has an additional cost of 10. 4 million. The team is looking for ways to pull that back through looking for additional, to remove access constraints during construction, but that is the current forecast and we are looking into how to mitigate that further. Moving to the calaveras stem in the project. Of course you have the e...