Vimarsana.com

Latest Breaking News On - Stephen kuczynski - Page 3 : vimarsana.com

Nuclear power: CO2 fix or cost disaster?

Surging gas prices are resurfacing a debate about how much nuclear will play a role in the U.S. electricity mix in coming decades.

Germany
Georgia
United-states
Tennessee-valley
California
Tennessee
United-kingdom
Idaho
South-carolina
Oak-ridge
Michigan
France

Georgia nuclear plant now delayed until 2022 as costs mount

Georgia nuclear plant now delayed until 2022 as costs mount JEA obligated to buy power from Vogtle plant Jeff Amy, Associated Press Tags:  File photo of construction at Plant Vogtle (Provided by Southern Company) ATLANTA – Georgia Power Co. said Tuesday that delays in completing testing means the first new unit at its Vogtle plant is now unlikely to start generating electricity before January at the earliest. The unit of Atlanta-based Southern Co. had in recent years been aiming to complete the first unit in November, but officials told investors last month that it would probably be finished in December. Company officials said Tuesday that testing began in late April, would take three weeks longer than expected and is unlikely to be completed before late June, adding more time to construction and startup.

Florida
United-states
Georgia
Atlanta
Jeremiah-haswell
Aaron-abramovitz
Stephen-kuczynski
Georgia-power-co
Tennessee-valley-authority
Southern-co
Southern-nuclear
Public-service-commission

Georgia nuclear plant now delayed until 2022 as costs mount

Georgia nuclear plant now delayed until 2022 as costs mount By Jeff Amy article ATLANTA (AP) - Georgia Power Co. said Tuesday that delays in completing testing means the first new unit at its Vogtle plant is now unlikely to start generating electricity before January at the earliest. The unit of Atlanta-based Southern Co. had in recent years been aiming to complete the first unit in November, but officials told investors last month that it would probably be finished in December. Company officials said Tuesday that testing began in late April, would take three weeks longer than expected and is unlikely to be completed before late June, adding more time to construction and startup.

Florida
United-states
Georgia
Atlanta
Jeremiah-haswell
Aaron-abramovitz
Stephen-kuczynski
Tennessee-valley-authority
Southern-co
Public-service-commission
Georgia-public-service-commission
Georgia-power-co

New Unit At Plant Vogtle Now Delayed Until 2022 As Costs Mount

Georgia Power Co. said Tuesday that delays in completing testing means the first new unit at Plant Vogtle is now unlikely to start generating electricity before January at the earliest. Georgia Power, a subsidiary Atlanta-based Southern Company, had in recent years been aiming to complete the first unit in November, but officials told investors last month that it would probably be finished in December. Company officials said Tuesday that testing began in late April, would take three weeks longer than expected and is unlikely to be completed before late June, adding more time to construction and startup. The additional month will add another $48 million to the cost of the two nuclear units being built alongside two existing units near Augusta.

Florida
United-states
Georgia
Jeremiah-haswell
Aaron-abramovitz
Stephen-kuczynski
Tennessee-valley-authority
Public-service-commission
Georgia-public-service-commission
Georgia-power-co
Florida-jacksonville-electric-authority
Southern-nuclear

vimarsana © 2020. All Rights Reserved.