New Road Bridge To Reopen Friday

  The Massachusetts Department of Transportation announced Thursday that the newly reconstructed New Road Bridge located over the West Branch of the Housatonic River will be reopened to traffic in the late afternoon on Friday, May 7.    The bridge was closed on Feb. 26, 2020, to allow crews to replace the existing bridge and upgrade existing utilities.   The cost of the bridge rehabilitation project is $1,734,102. The contractor for the project is JH Maxymillian.     The new 67-foot single-span precast, prestressed concrete NEXT, or Northeast Extreme Tee, beam superstructure will be supported by a cast-in-place reinforced concrete abutments. The new bridge will also be wider with a 28-foot roadway width providing two 10-foot-wide traffic lanes and two 4-foot-wide shoulders that will also accommodate pedestrians. 