448 infra projects report cost overrun of Rs 4.02 trn; 539 b

448 infra projects report cost overrun of Rs 4.02 trn; 539 behind schedule


As many as 448 central sector infrastructure projects have reported a cost overrun of over Rs 4.02 lakh crore as of February 21, 2021.
The monthly Flash Report by the Ministry of Statistics and Programme Implementation said that 539 projects are running behind schedule.
"Total original cost of implementation of the 1,739 projects was Rs 22,18,210.29 crore and their anticipated completion cost is likely to be Rs 26,20,618.44 crore, which reflects overall cost overruns of Rs 4,02,408.15 crore (18.14 per cent of original cost)," it said.
The expenditure incurred on these projects till January 2021 is over Rs 12.29 lakh crore, which is 46.92 per cent of the anticipated cost of the projects.

Related Keywords

, Programme Implementation , Ministry Of Statistics , Flash Report , Reliance Group , Reliance Infrastructure , Cost Overrun , Economy Of India , Economy Of Maharashtra , India , Union Budget Of India , Economy Of Bihar , Ministry Of Statistics And Programme Implementation , ப்ரோக்ராம் செயல்படுத்தல் , அமைச்சகம் ஆஃப் புள்ளிவிவரங்கள் , ஃபிளாஷ் அறிக்கை , நம்பகத்தன்மை குழு , நம்பகத்தன்மை உள்கட்டமைப்பு , பொருளாதாரம் ஆஃப் இந்தியா , பொருளாதாரம் ஆஃப் மகாராஷ்டிரா , இந்தியா , தொழிற்சங்கம் பட்ஜெட் ஆஃப் இந்தியா , பொருளாதாரம் ஆஃப் பிஹார் , அமைச்சகம் ஆஃப் புள்ளிவிவரங்கள் மற்றும் ப்ரோக்ராம் செயல்படுத்தல் ,