The Altoona Water Authority expects to start $30.8 million worth of work at the Bellwood reservoir in October or November, after years of delays.
Consulting engineer Gwin Dobson & Foreman is updating specifications and plans for the $20.9 million renovation of the dam and the $9.9 million renovation of the water treatment plant and has tentatively set up bid advertisements in July for the dam and in August for the plant, company President Mark Glenn told the board Thursday.
The authority will pay for the projects with $30.9 million that Pennvest awarded in January, several weeks after the Department of Environmental Protection had issued a permit for the dam and five months after it had issued a permit for the plant.

Related Keywords

Germany , William Kibler , Gwin Dobson , Mark Perry , Michael Sinisi , Mark Glenn , Department Of Environmental Protection , Altoona Water Authority , President Mark Glenn , Environmental Protection , General Manager Mark , Bellwood Borough , Staff Writer William Kibler , ஜெர்மனி , வில்லியம் கிப்லெர் , குவீன் டாப்சன் , குறி பெர்ரி , குறி க்ளென் , துறை ஆஃப் சுற்றுச்சூழல் ப்ரொடெக்ஶந் , அல்தூனா தண்ணீர் அதிகாரம் , சுற்றுச்சூழல் ப்ரொடெக்ஶந் , ஜநரல் மேலாளர் குறி , பெல்வுட் பெருநகர , ஊழியர்கள் எழுத்தாளர் வில்லியம் கிப்லெர் ,

© 2025 Vimarsana