Causeway Closure To Start One Month Early


Petitcodiac River Bridge under construction (submitted)
In less than six weeks, the causeway over the Petitcodiac River linking Moncton and Riverview will be closing.
The provincial government announced today it is moving up the closure date to April 5 instead of May as originally planned.
The Petitcodiac River Bridge which is replacing the causeway is expected to be ready to open in October.
The closure is required to realign the river channel under the new bridge, as well as to decommission the existing gate structure and construct the approaches and bridge connections.
“As work on the project is progressing well, we are starting the causeway’s six-month full closure one month earlier than planned. It will reopen to traffic in October instead of November,” said Transportation and Infrastructure Minister Jill Green.

Related Keywords

Moncton , New Brunswick , Canada , Petitcodiac River , , Petitcodiac River Bridge , Petiticodiac River Bridge , Infrastructure Minister Jill , Gunningsville Bridge , Petitcodiac Bridge , Bridgedale Boulevard , Gunningsville Boulevard , Runneymeade Road , மோன்க்டொன் , புதியது பிரன்சுவிக் , கனடா , பெட்டிட்கோடியாக் நதி , பெட்டிட்கோடியாக் நதி பாலம் , உள்கட்டமைப்பு அமைச்சர் ஜில் , குண்ணிங்ஸ்வில்லெ பாலம் , பெட்டிட்கோடியாக் பாலம் , பிரிட்ஜ்டேல் பவுல்வர்டு , குண்ணிங்ஸ்வில்லெ பவுல்வர்டு ,