EWP-EDF wave project nears construction milestone


Advertisement
Pursuant to the engineering co-ordination permit from the Municipality of Tel-Aviv Jaffa (permit number 2020-3249) Eco Wave Power has announced that it nears completion of the wall reinforcement works, meant to enable the installation of floaters on the sea wall of the Port of Jaffa, Israel.
The works so far have included clearing the top cement layer of the relevant sections of the sea wall, followed by adding two layers of steel rebars for reinforcement and finally, in several days (in accordance with weather conditions), the final step will be completed, which is the creation of a new cement layer, which shall provide the necessary support for the installation of the floaters. In parallel, the company is in an advanced production process of the first set of floaters. Upon production completion, the company will gradually commence installation of floaters, supporting structures, and hydraulic pipes onto the new cement layers.

Related Keywords

Israel , Israeli , Alex Gleizer , Aviv Jaffa , Israeli Air , Israeli Railway Company , Israeli Electric Company , Israeli Energy Ministry , Energy Global , Tel Aviv Jaffa , Eco Wave Power , Israeli Air Force , Inna Braverman , Eco Wave , Israeli Energy , இஸ்ரேல் , இஸ்ரேலி , அவிவ் ஜ்யாஃபா , இஸ்ரேலி அேக , இஸ்ரேலி ரயில்வே நிறுவனம் , இஸ்ரேலி மின்சார நிறுவனம் , இஸ்ரேலி ஆற்றல் அமைச்சகம் , ஆற்றல் உலகளாவிய , தொலைபேசி அவிவ் ஜ்யாஃபா , சூழல் அலை பவர் , இஸ்ரேலி அேக படை , இன்ன துணிச்சலான , சூழல் அலை , இஸ்ரேலி ஆற்றல் ,

© 2025 Vimarsana