Freeport LNG Second Loading Dock Inches Closer to Restart |

Freeport LNG Second Loading Dock Inches Closer to Restart | Marcellus Drilling News

Freeport LNG’s export terminal with three liquefaction “trains” shut down in June 2022 after an explosion and fire (see Explosion Rocks Freeport LNG Export Plant – Offline for 3 Weeks). What was initially thought to be a three-week outage lasted for ten months! The plant finally returned online in March of this year (see Freeport