Share price 2 March 2021 | 10:05am StockMarketWire.com - Oil and gas company Hurricane Energy said it plans to drill a second production well at the Lancaster development programme was thrown into doubt as the proposed side-track appeared to be more complex than initially expected. The company concluded that it would not be possible to drill the well during the 2021 summer weather window without unacceptable operational and cost risk. 'This proposed side-track is more complex in nature than previous wells on Lancaster due to the incorporation of an intelligent completion and the challenges of delivering the well trajectory from the side-track location,' the company said.