Main Street Update 6.1.21 Fulton Street intersection work will continue into next week. With any luck, we may have some concrete poured before the end of next week. Concrete sidewalk work will continue next week with new sidewalk going in from 108 N Main (Sundazzle Grooming) to 100 N Main (Edwards Jones). New sidewalk is also planned for from 121 N Main (Stewart Title) to 103 N Main (Main Street Marketplace). Base aggregate placement will continue next week. Work will focus on getting the Fulton Street intersection ready for concrete and then continuing preparing the road to the north. There was a major power-outage on 5/28; the outage was not the fault of the construction from the Main St work.