MRT-7 to open by end-2022 February 19, 2021 | 6:09 pm San Miguel Corporation (SMC) on Friday said the Metro Rail Transit Line 7 (MRT-7) project is now 54% complete, on track for its opening by the end of 2022. “We have already completed a significant amount of civil works, including the installation of bored piles, girders, foundational works on stations, and we have been installing rails or tracks. At the same time, E&M works have also advanced significantly,” SMC President Ramon S. Ang said in a statement on Friday. Around 6.2 kilometers (km) of the 13.5-km elevated section is complete, while 4.8 km out of 6.9 km of the at-grade section and 1.5 km of the 1.9 km tunnel section are done. Civil works and electrical/mechanical works are both more than halfway done.