Overall progress of metro-rail construction reaches 61.49pc:

Overall progress of metro-rail construction reaches 61.49pc: Quader | Bangladesh Sangbad Sangstha (BSS)


Overall progress of metro-rail construction reaches 61.49pc: Quader
167
File photo
DHAKA, April 22, 2021 (BSS) – Road Transport and Bridges Minister Obaidul Quader today said the overall progress of the country’s first metro-rail construction work stands at 61.49 percent.
“Overall progress of the metro-rail construction work reached 61.49 percent. The physical progress of the first phase construction of the metro-rail from Uttara to Agargaon is 83.52 percent,” he told a regular press conference at his official residence here.
Quader said combined progress of electrical and mechanical system and procurement of rolling stock (rail coaches) and depot equipment is 52.22 percent.
The first elevated metro-rail will have 24 sets of 144 coaches and each set will have six coaches, he said.

Related Keywords

Tungipara , Bangladesh General , Bangladesh , Uttara , Rangpur , Japan , Mongla Port , Khulna , Gopalganj , Dhaka , Japanese , Bangabandhu Sheikh Mujibur Rahman , Obaidul Quader , Dhaka Mass Transit Company Limited , , Road Transport , Bridges Minister Obaidul Quader , Uttara Depot , Kobe Based Japanese , Gopalganj Zone , Nation Bangabandhu Sheikh Mujibur Rahman , Bangladesh Road Transport Authority , பங்களாதேஷ் ஜநரல் , பங்களாதேஷ் , உத்தாரா , ரங்க்பூர் , ஜப்பான் , கூழ்ந , கோபல்காஞ்ச் , டாக்கா , ஜப்பானிய , பங்கபந்து ஷேக் முஜிபூர் ரஹ்மான் , டாக்கா நிறை போக்குவரத்து நிறுவனம் வரையறுக்கப்பட்டவை , சாலை போக்குவரத்து , உத்தாரா டிப்போ , தேசம் பங்கபந்து ஷேக் முஜிபூர் ரஹ்மான் , பங்களாதேஷ் சாலை போக்குவரத்து அதிகாரம் ,