Panama City Beach to begin Front Beach Road projects in 2021

Panama City Beach to begin Front Beach Road projects in 2021


In a presentation during the meeting, David Campbell, manager of city's Community Redevelopment Agency, said the four projects to begin this year are:
Front Beach Road Segment 3, which will cost about $28 million, break ground in late April or early May and take about 18 months to complete. It will redevelop Front Beach Road from about Winn-Dixie to Lullwater Drive, as well as on State 79 from Front Beach Road to Panama City Beach Parkway. A roundabout also will be installed at the intersection of State 79 and Front Beach Road. 
The construction of a signalized intersection at the crossing of Powell Adams Road and Front Beach Road. It will cost more than $4 million, break ground in late May and take about a year to complete. 

Related Keywords

Panama , Mark Sheldon , Nathan Cobb , Geoff Mcconnell , Paul Casto , David Campbell , Community Redevelopment Agency , Panama City Beach Council , Community Redevelopment Plan , City Beach Front Road , Front Beach Road , Front Beach Road Community Redevelopment Plan , Panama City Beach , Beach Road Segment , Front Beach , Lullwater Drive , Powell Adams Road , Alf Coleman Road , Panama City Beach Parkway , Hutchison Boulevard , Hills Road , Richard Jackson , Councilman Geoff Mcconnell , பனாமா , குறி ஷெல்டன் , நாதன் கோப் , ஜியோஃப் ம்க்காநெல் , பால் காஸ்டோ , டேவிட் கேம்ப்பெல் , பனாமா நகரம் கடற்கரை சபை , சமூக மறுவடிவமைப்பு திட்டம் , முன் கடற்கரை சாலை , முன் கடற்கரை சாலை சமூக மறுவடிவமைப்பு திட்டம் , பனாமா நகரம் கடற்கரை , முன் கடற்கரை , போவல் ஆடம்ஸ் சாலை , ஆல்ப் கோல்மேன் சாலை , பனாமா நகரம் கடற்கரை பூங்கா , ஹட்ச்சன் பவுல்வர்டு , மலைகள் சாலை , ரிச்சர்ட் ஜாக்சன் , கவுன்சிலன் ஜியோஃப் ம்க்காநெல் ,

© 2025 Vimarsana