The Whittaker Street project has hit a snag, being delayed a bit due to a decision by Shawnee City Commissioner to reject the three submitted bids.
Last month, Public Works Director Brad Schmidt brought three submitted bids to Shawnee City Commissioners for the city's planned Whittaker Street Rehabilitation project, when the item was deferred to allow time for assessment of the bids.
This week City Engineer Seth Barkhimer urged commissioners to reject the bids; the board chose to favor his request, voting unanimously to reject the bids.
Bids
In March Schmidt said the city had estimated cost for the project around $500,000 — about $134,000 less than the lowest bid that came in.

Related Keywords

Seth Barkhimer , Vickyo Misa , Brad Schmidt , Bellen Inc , Nash Construction Co , Wynn Construction Co , Whittaker Street , Shawnee City Commissioner , Public Works Director Brad Schmidt , Shawnee City Commissioners , Whittaker Street Rehabilitation , City Engineer Seth Barkhimer , March Schmidt , Tech Paving , Wynn Construction , Nash Construction , Horace Mann Elementary , பிராட் ஶ்மிட் , நஷ் கட்டுமானம் இணை , விந் கட்டுமானம் இணை , விட்டேக்கர் தெரு , ஷாவ்னி நகரம் ஆணையர் , பொது வேலை செய்கிறது இயக்குனர் பிராட் ஶ்மிட் , ஷாவ்னி நகரம் ஆணையர்கள் , விட்டேக்கர் தெரு புனர்வாழ்வு , தொழில்நுட்பம் நடைபாதை , விந் கட்டுமானம் , நஷ் கட்டுமானம் , ஹாரெஸ் மான் தொடக்க ,