Greek duo to wire 330MW onshore giant
A joint venture of Hellenic Cables and Asso Subsea has been selected by Terna Energy for the design, manufacturing, supply and installation of a subsea cable to connect the 330MW Kafireas 2 wind farm on the island of Evia to mainland Greece. Kafireas 2 is located on the southern-most part of the island and will be connected to the national grid at IPTO’s 150kV Lavrion substation. The link will include approximately 70km of 150kV three-core composite submarine cables and 11km of 150kV single-core underground onshore wires, as well as all accessories, joints, terminations and fittings. Produc...