Q&D Construction Completes Echo Summit Job : CEG
Tue June 01, 2021 - West Edition #12 Irwin Rapoport â CEG Correspondent Crews from Q&D Construction recently completed the Echo Summit bridge replacement three months ahead of schedule thanks to an accelerated bridge construction (ABC) method. Employing an accelerated bridge construction method (ABC), Q&D Construction was able to complete the California Department of Transportation's $14.1 million U.S. Highway 50 Echo Summit Sidehill Viaduct Replacement Project three months ahead of schedule. The original bridge (two lanes, 129-ft. long and two spans), constructed in 1939 for $25,000 ...