Bruner Hall restoration nearing spring completion
The Antelope larsonjt2@lopers.unk.edu Bruner Hall has been undergoing restoration work since a pipe burst due to cold weather in February, flooding labs and classrooms throughout all four floors. Two months later, the hall is reoccupied, but work is expected to continue for months to come. The restoration has been led by C-Tech Restoration with assistance from Yellow Van Cleaning and Restoration. In the first week, the restoration crew committed 1,000 hours of work to the project. Since then, restoration has been completed on a majority of the emergency repairs. “Most areas have been reo...