Invercargill CBD block development ticking along
Invercargill Central reported three-quarters of the concrete precast panels of the anchor-tenant Farmers building are in place. The Farmers store is expected to be completed by mid-2022, with food outlets set to open about September 2022, and the rest of the stores to open by the end of 2022. Last week the concrete was poured for the second floor of the car park, and construction of the HWR office tower begun, however it would be several weeks before progress of the tower could be seen above ground. There would be space for more than 600 cars in the block development. The HWR office towe...