SSE Renewables turns sod on Lenalea
SSE Renewables and its co–development partner Coillte Renewable Energy have begun construction of their joint 30MW Lenalea wind project in central Donegal. Delivery of Vestas turbines to Lenalea is expected to commence in spring 2023, with installation of the seven Vestas V117-4.2MW turbines in 4.3MW operating mode scheduled to take place at the site over the course of summer 2023. Full wind farm commissioning and completion is expected in late 2023. Delivery of the Lenalea Wind Farm project represents a joint total capital investment of around €40m by 50:50 co-development partners SSE Re...